• More paint (primer), and flooring prep.
Some of the new flooring is due to arrive next week in order to "acclimate" to the
facility.
• Jennings Hall: Though all of the attention has mostly focused on the main building and the sanctuary, things are happening in Jennings Hall also. Thanks to a large group of volunteers, JH has been cleaned out, organized (by room), and many older/unwanted items discarded. Separately, the JH kitchen has also been cleaned out and organized and we received a donation of a new cabinet freezer. Enough work has been done that we can now hold some regular meetings in Jennings Hall. THANKS TO EVERYONE WHO HAS HELPED!