UPDATES: Week of February 25
The restoration of our facility continued to progress this week.
• A small team of church members spent Saturday afternoon removing items from walls, doorknobs, and old window-crank mechanisms.
• Painters applied primer to new drywall in sanctuary and cinder block walls in the main hallway and classrooms.
• New LED ceiling fixtures have been installed in the women's restroom and kitchen
• A low balcony wall was built around the new stairs
• Sanctuary hanging light fixtures were removed for cleaning
• New gutters were installed all the way around the main building